Preparation for the renovation is progressing well.
After forming a Renovation Group of concerned people, Corine Keus was selected as architect. Three working sessions have now taken place and a sketch design, an element budget and a preliminary planning have emerged. We in the renovation group are very happy with the design. Below you can see the design we discussed at our Oct. 25 meeting.
We invite everyone to come on Nov. 26 at 1:30 p.m. Then Corine will explain the design and how it came about. By then, the schedule will be further tightened. As it looks now, the renovation will take place from June – September 2023. Then the Gym will be completely closed!
Learn more and follow the news at the Gymzaal.org. And don’t forget to sign up for their newsletter. This will keep you informed of all the new developments surrounding the remodel!